CVPPL starts Stringing Works of Transmission Line 14-Jan-2026

CVPPL Started the Stringing Works of Transmission system for evacuation of power from Pakal Dul, Kiru and Kwar HE Projects of CVPPL
In another significant development, Stringing Works has been started on 13.01.2026 for 400kV Double Circuit (Triple HTLS Conductor) Transmission Line from Pot Head Yard of Kiru HEP to Kishtwar Pooling Station including LILO of one Circuit of 400kV D/c (Triple HTLS Conductor) Kiru - Kishtwar line at Pot Head Yard of Kwar & Pakal Dul HE Projects.
The said transmission line shall be completed well within schedule to match the commissioning of CVPPL Projects and these Stringing Works, shall facilitate in timely completion of above transmission lines.