CVPPL is a Joint Venture Company between NHPC (51%) and JKSPDC (49%) formed at the initiative of Government of J&K and Government of India to harness the vast hydro potential of river Chenab. The Company has been incorporated on 13.06.2011.
CVPPL has been entrusted with construction of following projects on Build, Own, Operate and Maintain (BOOM) basis with aggregate installed capacity of 3094 MW.
Pakal Dul HE Project (1000 MW) |
Under active construction Foundation stone of the project has been laid by Hon'ble Prime Minister of India on 19.05.2018. |
Kiru HE Project (624 MW) |
Under active construction Foundation stone of the project has been laid by Hon’ble Prime Minister of India on 03.02.2019. |
Kwar HE Project (540 MW) |
Under active construction Foundation stone of the project has been laid by Hon’ble Prime Minister of India on 22.04.2022. |
Kirthai-II HE Project (930 MW) |
MoU signed between JKPDD and NHPC on 03.01.2021 wherein the implementation of the project is entrusted to CVPPL. Obtaining pending clearances of the project are under progress.
|